17) If removed, install inspection doors 213 and 214 - refer to 06-30-00.
18) Install the cowling under hull 218.
19) Install engine cowlings - refer to 71-10-01.
20) Test the emergency distribution system - refer to Page 501.
21) Install inspection door 211 L and, if necessary, inspection door 211 R - refer to 06-30-00.
WA
Validity : OPTION
Page 602
37-12-00
(BA) SEP 04
 
Emergency distribution - Inspection / Check
Figure 601
AAAA
Validity : OPTION 37-12-00Page 603
(BA) SEP 04
 
Emergency distribution - Inspection / Check
Figure 602
AAAA
Validity : OPTION 37-12-00Page 604
(BA) SEP 04
 
ELECTROMECHANICAL VACUUM PUMP
REMOVAL / INSTALLATION
1. REMOVAL OF THE ELECTROMECHANICAL VACUUM PUMP (Figures 401 and 401A)
A. Tools and consumable materials
- Blanking caps and plugs
B. Procedure
1) Remove the cowling under hull 218.
2) Open "AUX SUCT" circuit breaker on the circuit breaker panel.
3) Install the warning sign prohibiting main switch-breaker operation.
WARNING
DO NOT OPERATE
MAINTENANCE WORK IN PROGRESS
4) Loosen clamp (9) and disconnect hose (10). Blank off.
5) Mark the wires and disconnect the electrical power supply. Retain filter (7).
6) Remove bolt (11) and washer (12).
7) Remove bolts (3), washers (2) and electromechanical pump (4). Retain spacers (16).
8) If electromechanical vacuum pump (4) is to be replaced, perform the following operations :
a) Mark the orientation of the pump with respect to support (5) and the orientation of unions (8) and (14)
with respect to the pump.
b) Loosen clamps (6) and remove support (5).
c) Remove unions (8) and (14). Blank off.
d) Mark its position and then remove bonding strap (13). Reinstall its attaching hardware on the pump
body.
2. INSTALLATION OF THE ELECTROMECHANICAL VACUUM PUMP (Figures 401 and 401A)
A. Tools and consumable materials
- Varnish (TB 07-906)
- Lubricant (TB 06-903C)
B. Procedure
1) If electromechanical vacuum pump (4) has been replaced, perform the following operations :
a) Install bonding strap (13) at the location marked during removal - refer to 20-00-12.
b) Clean and then spray the threads of unions (8) and (14) with lubricant (TB 06-903C).
c) Install unions (8) and (14) as marked during removal.
 
d) Secure support (5) to the pump with clamps (6). Observe the orientation marked during removal.
2) Insert bolts (3) and washers (2) into vibration isolators (15). Install spacers (16) and secure the pump assembly.
3) Secure bonding strap (13) with bolt (11) and washer (12) - refer to 20-00-12.
 